Pattern 4: Job Queue Integration

Problem​

Manual execution requires:

  • User monitoring every 30 minutes
  • Manual re-runs for days
  • Risk of forgetting to re-run
  • No execution during nights/weekends

Solution​

Configure Job Queue to automatically re-run the report every 30 minutes until BatchLimitReached = false.

Prerequisites​

1. GuiAllowed Protection​

Wrap ALL user interactions:

// ✅ Correct: Protected messages
if GuiAllowed then
Message('Processing complete');

if GuiAllowed then
Window.Open('Progress...');

// ❌ Wrong: Blocks Job Queue
Message('Processing complete'); // Job Queue can't dismiss
Confirm('Continue?', false); // Job Queue can't answer
Error('Failed'); // Stops Job Queue permanently

2. Silent Confirmation​

trigger OnInitReport()
begin
// Only confirm if manual (GUI) execution
if GuiAllowed then
if not Confirm('Run this process?', false) then
Error('Cancelled by user');
// Job Queue bypasses this check
end;

3. Clean Exit on Batch Limit​

trigger OnPostReport()
begin
// Don't Error() on batch limit — just log and exit
if BatchLimitReached then begin
// Log execution
ExecutionLog.LogExecution(...);
// Exit cleanly (Job Queue will re-run)
exit;
end;
end;

Job Queue Entry Configuration​

Basic Setup​

Navigate to: Job Queue Entries page

Required fields:

FieldValueNotes
Object Type to RunReport
Object ID to Run50000Your batch report ID
Report Request Page Options(default)Can set filters if needed
Maximum No. of Attempts to Run100CRITICAL: Default is 1
Recurring JobYesAuto-restart after run
No. of Minutes between Runs30Balance: progress vs system load

Schedule​

Option A: 24/7 Processing

Run on Mondays: Yes
Run on Tuesdays: Yes
Run on Wednesdays: Yes
Run on Thursdays: Yes
Run on Fridays: Yes
Run on Saturdays: Yes
Run on Sundays: Yes
Starting Time: 00:00:00
Ending Time: 23:59:59

Option B: Nights Only (recommended for production)

Starting Time: 22:00:00  (after business hours)
Ending Time: 08:00:00 (before users arrive)
All days: Yes

Option C: Weekends Only (minimal impact)

Run on Mondays: No
Run on Tuesdays: No
Run on Wednesdays: No
Run on Thursdays: No
Run on Fridays: No
Run on Saturdays: Yes
Run on Sundays: Yes
Starting Time: 00:00:00
Ending Time: 23:59:59

Priority​

Priority: 500  (default)

Lower number = higher priority. Set to 1000 if you want other jobs to run first.

Execution Flow​

First Night (22:00 - 08:00)​

22:00 → Execution 1: 50,000 processed, BatchLimit = true
22:30 → Execution 2: 50,000 processed, BatchLimit = true
23:00 → Execution 3: 50,000 processed, BatchLimit = true
23:30 → Execution 4: 50,000 processed, BatchLimit = true
00:00 → Execution 5: 50,000 processed, BatchLimit = true
...
07:30 → Execution 20: 50,000 processed, BatchLimit = true
08:00 → Stop (business hours)

Total: 1,000,000 records processed
Remaining: 1,500,000

Second Night​

22:00 → Execution 21: 50,000 processed, BatchLimit = true
...
07:30 → Execution 40: 50,000 processed, BatchLimit = true
08:00 → Stop

Total: 2,000,000 records processed
Remaining: 500,000

Third Night​

22:00 → Execution 41: 50,000 processed, BatchLimit = true
22:30 → Execution 42: 50,000 processed, BatchLimit = true
...
23:30 → Execution 45: 50,000 processed, BatchLimit = true
00:00 → Execution 46: 0 processed, BatchLimit = false ✅

Job Queue stops (all records processed)

Monitoring​

View Job Queue Status​

Navigate to: Job Queue Entries → Your entry

Key fields to monitor:

Status: Ready / In Process / Error
Last Ready State: [timestamp of last successful run]
Number of Attempts to Run: 45 (increments each run)
Earliest Start Date/Time: [next scheduled run]

View Execution Log​

Navigate to: Batch Sync Execution Log List

SELECT TOP 10 
"Entry No.",
"Execution Started At",
"Duration (Minutes)",
"Total Processed",
"Batch Limit Reached"
FROM "Batch Sync Execution Log"
ORDER BY "Entry No." DESC;

Example output:

Entry | Started At       | Duration | Total   | Batch Limit
------|------------------|----------|---------|------------
45 | 2026-05-29 00:00 | 12.3 | 0 | No ✅
44 | 2026-05-28 23:30 | 13.1 | 50,000 | Yes
43 | 2026-05-28 23:00 | 12.8 | 50,000 | Yes

View Progress​

Navigate to: Batch Sync Progress List

Table Name              Progress %  Remaining   ETA
--------------------- ------------- ----------- ------------------
Sales Header 100% 0 Completed
Sales Line 100% 0 Completed
Sales Shipment Line 89% 55,000 Thu 22:15
Sales Invoice Line 45% 275,000 Fri 01:30

Troubleshooting​

Issue 1: Job Queue Stops After First Run​

Symptom: Only one execution, then status = "On Hold"

Cause: "Maximum No. of Attempts to Run" = 1 (default)

Fix:

  1. Open Job Queue Entry
  2. Set "Maximum No. of Attempts to Run" = 100
  3. Set "Status" = "Ready"

Issue 2: Job Queue Shows "Error"​

Symptom: Status = "Error", Last Error: "..."

Causes:

  • Unprotected Error() call in report
  • Unprotected Message() or Confirm() call
  • Actual runtime error (division by zero, record not found, etc.)

Fix:

  1. Read error message in "Error Message" field
  2. Fix the code issue
  3. Set "Status" = "Ready" to restart

Issue 3: Job Queue Runs During Business Hours​

Symptom: Users report slowness during work hours

Fix:

  1. Set "Starting Time" = 22:00:00
  2. Set "Ending Time" = 08:00:00

Issue 4: Job Queue Runs Too Frequently​

Symptom: System overloaded, reports slow

Fix: Increase "No. of Minutes between Runs" from 30 → 60

Issue 5: Job Queue Runs Too Infrequently​

Symptom: Progress too slow, will take weeks

Fix:

  • Option A: Decrease interval from 30 → 15 minutes
  • Option B: Increase batch size from 50,000 → 75,000
  • Option C: Enable 24/7 execution

Best Practices​

1. Test First​

Before enabling Job Queue:

  1. Run report manually 3-5 times
  2. Verify batch limiting works
  3. Check progress updates correctly
  4. Confirm execution log entries created

2. Start Conservatively​

First deployment:
- Interval: 30 minutes (not 5)
- Schedule: Nights only (not 24/7)
- Batch size: 50,000 (not 100,000)

Monitor for 1-2 days, then adjust if needed

3. Monitor Actively (First Week)​

Check daily:

  • Number of executions completed
  • Average duration per execution
  • Any errors in Job Queue Log Entry
  • Progress % advancement

4. Plan for Completion​

Estimated completion time = (Remaining records) / (Records per hour) / (Hours per day)

Example:

Remaining: 2,500,000 records
Speed: 100,000 records/hour (2 executions/hour × 50K/exec)
Schedule: 10 hours/night (22:00 - 08:00)

Days needed: 2,500,000 / 100,000 / 10 = 2.5 nights

5. Clean Up After​

When BatchLimitReached = false (all done):

  1. Set Job Queue Entry Status = "On Hold" (stop future runs)
  2. Optional: Delete Job Queue Entry
  3. Optional: Delete progress tracking tables
  4. Document completion date for audit

Security Considerations​

Permissions Required​

Job Queue Entry needs:

Permissions = tabledata "My Table 1" = RIMD,
tabledata "My Table 2" = RIMD,
tabledata "Batch Sync Progress" = RIMD,
tabledata "Batch Sync Execution Log" = RIMD;

User Context​

Job Queue runs as "NT AUTHORITY\SYSTEM" (service account).

Ensure:

  • Report doesn't rely on UserId() for business logic
  • No user-specific filters that break in Job Queue context
  • Error messages don't expose sensitive data (logged to Job Queue Log)
  • Pattern 1: Batch-Limited Report (what the Job Queue runs)
  • Pattern 2: Progress Tracking Tables (what you monitor)
  • Pattern 5: Progress Monitoring Pages (how you monitor)